The city of Englewood has issued a report updating the community on the status of local development projects.
This item is available in full to subscribers.
If you're a print subscriber, but do not yet have an online account, click here to create one.
Click here to see your options for becoming a subscriber.
If you made a voluntary contribution in 2023-2024 of $50 or more, but do not yet have an online account, click here to create one at no additional charge. VIP Digital Access includes access to all websites and online content.
Here's a roundup provided by the city:
Swedish Medical Center
501 East Hampden Avenue
Project: Five-story vertical expansion; 115,371 square feet.
Status: Plans are under review.
Synergy Medical Office Building
506 East Hampden Avenue
Project: A five-story, mixed-use development with 14,000 square feet of retail (ground floor) and 104,000 square feet of medical office space. The building will have self-contained parking offering valet parking and 325+ parking spaces in a covered structure.
Status: Construction continues
Iron Works Village
601 West Bates Avenue
Project: 136 townhomes, condominiums, and single-family for sale units.
Status: Construction continues.
Winslow Crane Apartments
3002 South Huron Street
Project: 203 for-lease units, 12 three-story walkups.
Status: A virtual neighborhood meeting was held on June 18. A Planned Unit Development (PUD) application was submitted on June 29.
3500 South Corona Street
Project: 44-unit for-sale residential building.
Navajo Apartments
4201 South Navajo Street
Project: Five stories, 146 residential units
Status: Building permit under review
2140 South Zuni Street
Project: Sixty-four townhomes; for sale units.
Status: A formal planned unit development application was filed on Dec. 6, 2019. The applicant will be hosting a neighborhood meeting within the next two months.
3525 - 3545 South Emerson Street
Project: 25 townhomes; for sale units
Status: Foundation work continues
1280 East Hampden Avenue
Project: 18 townhomes.
Hilltop
3800 South Broadway
Project: Three-story building comprising eight apartments above a 2,800 square foot commercial space
Stautus: Construction continues. The property owner is inquiring about a liquor license for a prospective restaurant tenant.
Englewood Dental Center
3401 South Broadway, Suite 180
Status: Plans have been approved and building permits issued.
3507 South Ogden Street
Project: Six townhomes; for sale units
3531 South Pennsylvania Street
Project: 12 townhomes; for sale units
Status: Certificate of Occupancy issued in April.
3325 South Santa Fe Drive
Project: 10,200-square-foot storage facility
Status: Plans have been approved and permit issued. Construction has started.
Front Range Pharmacy
3401 South Broadway, Suite 160
Project: Tenant finish
Status: Certificate of occupancy issued March 31. Now open for business.
The Hive on Broadway
200 West Belleview Avenue
Project: Multi-use remodel.
Status: Plans have been approved.
Mango Tree Coffee
3498 South Broadway
Status: Interior tenant finish continues.